ANNA ELEMENTARY SCHOOL ROAD, CITY OF ANNA
- Concrete paving for school access road in Anna.
SERENA ADDITIONS, CITY OF BEDFORD
- Earth movement, concrete paving, and sidewalk
- Concrete paving, soil compaction as per city, installation of rock entrance/exit, sidewalk and flumes.
BURSEY ROAD PHASE 2, CITY OF WATAUGA
- Concrete paving, sidewalks, driveway, Inlets, Manholes, Water & Storm drain, Excavation & stabilization.
- Removal of existing storm drains, curb inlets, headwalls, concrete flat works and installations of new 18” to 30” RCP pipes, drain vaults, flume walls.
- 12” and 6” water line installation with gate valve
- Subgrade stabilization of around 15,000 SY, Concrete Pavements and drive ways with sidewalks and ADA ramps.
SIDEWALK IMPROVEMENTS, CITY OF PLANO
- Sidewalk, Ramp and Alley Improvements.
- Removal and replacement of concrete street pavement, concrete drive ways, concrete alley pavement and around 90,000 SF of concrete sidewalks and ADA ramps.